Raymond Building - Deferred maintenance / Updates

February 2022 Update

(updates from October 2021 update appear in bold)

Timeline

(subject to change)

Affected areas Scope of work Impact Mitigation measures
October 12, 2021 to November 30, 2022

Phase 1 (Raymond courtyard)

Mobilization area  Moderate levels of noise and access restrictions. Access restrictions and new access points will be communicated through signage.
October 12, 2021 to November 2022

North section of the Raymond basement, including building extension on the north side

General construction High levels of noise and vibrations at the beginning of the project and moderate to high levels in the construction zone. Multiple shutdowns, areas will not be accessible. The entire area is a construction zone.
October 12, 2021 to May 2022 Phase A (Raymond interior, central area) General construction Moderate to high levels of noise in the construction zone. Multiple shutdowns, some areas will not be accessible.

The users have been relocated but the building remains in operation. Signage will be installed to advise users of new access points.

Classrooms in Octagon area will remain operational.

April 15, 2022 to August 2022 Phase B (Raymond Building - complete closure, Barton link - partial closure, cafeteria) General construction Moderate to high levels of noise in the construction zone. Multiple shutdowns, areas will not be accessible.

The users will have been relocated and the building will be closed.

April 15, 2022 to November 30, 2022 Phase 2 (Raymond exterior, Barton link exterior) Roof and mechanical system installation Loud noise and vibrations and access restrictions. Noisy work will be done during the summer. Access restrictions and new access points will be communicated through signage.
September 1, 2022 to mid-July 2023 Phase C (Raymond West Wing) General construction Moderate to high levels of noise in the construction zone. Multiple shutdowns, areas will not be accessible.

The users have been relocated but the building remains in operation. Signage will be installed to advise users of new access points.

Classrooms in Octagon area will remain operational.

January 2, 2023 to July 24, 2023 Phase 3 (Raymond exterior)

Roof, French drains and entrance

Low to moderate levels of noise (general construction activity) and access restrictions.

Access restrictions and new access points will be communicated through signage.
April 1, 2023 to July 24, 2023 Phase 4 (Raymond exterior) Landscaping Low levels of noise, access restrictions. Access restrictions and new access points will be communicated through signage.

 