February 2022 Update
(updates from October 2021 update appear in bold)
Timeline (subject to change) |
Affected areas | Scope of work | Impact | Mitigation measures |
---|---|---|---|---|
October 12, 2021 to November 30, 2022 |
Phase 1 (Raymond courtyard) |
Mobilization area | Moderate levels of noise and access restrictions. | Access restrictions and new access points will be communicated through signage. |
October 12, 2021 to November 2022 |
North section of the Raymond basement, including building extension on the north side |
General construction | High levels of noise and vibrations at the beginning of the project and moderate to high levels in the construction zone. Multiple shutdowns, areas will not be accessible. | The entire area is a construction zone. |
October 12, 2021 to May 2022 | Phase A (Raymond interior, central area) | General construction | Moderate to high levels of noise in the construction zone. Multiple shutdowns, some areas will not be accessible. |
The users have been relocated but the building remains in operation. Signage will be installed to advise users of new access points. Classrooms in Octagon area will remain operational. |
April 15, 2022 to August 2022 | Phase B (Raymond Building - complete closure, Barton link - partial closure, cafeteria) | General construction | Moderate to high levels of noise in the construction zone. Multiple shutdowns, areas will not be accessible. |
The users will have been relocated and the building will be closed. |
April 15, 2022 to November 30, 2022 | Phase 2 (Raymond exterior, Barton link exterior) | Roof and mechanical system installation | Loud noise and vibrations and access restrictions. | Noisy work will be done during the summer. Access restrictions and new access points will be communicated through signage. |
September 1, 2022 to mid-July 2023 | Phase C (Raymond West Wing) | General construction | Moderate to high levels of noise in the construction zone. Multiple shutdowns, areas will not be accessible. |
The users have been relocated but the building remains in operation. Signage will be installed to advise users of new access points. Classrooms in Octagon area will remain operational. |
January 2, 2023 to July 24, 2023 | Phase 3 (Raymond exterior) |
Roof, French drains and entrance |
Low to moderate levels of noise (general construction activity) and access restrictions. |
Access restrictions and new access points will be communicated through signage. |
April 1, 2023 to July 24, 2023 | Phase 4 (Raymond exterior) | Landscaping | Low levels of noise, access restrictions. | Access restrictions and new access points will be communicated through signage. |