Raymond Building - Deferred maintenance / Updates

Overview of the project

Floor plans and scheduling

October 2021 Update

Timeline

(subject to change)

Affected areas Scope of work Impact Mitigation measures
October 12, 2021 to November 30, 2022

Phase 1 (Raymond exterior)

Roof, French drain and entrance Moderate levels of noise and access restrictions. Access restrictions and new access points will be communicated through signage.
October 12, 2021 to November 2022

North section of the Raymond basement, including building extension on the north side

General construction High levels of noise and vibrations at the beginning of the project and moderate to high levels in the construction zone. Multiple shutdowns, areas will not be accessible. The entire area is a construction zone.
October 12, 2021 to April 15, 2022 Phase A (Raymond interior, octagon area) General construction Moderate to high levels of noise in the construction zone. Multiple shutdowns, areas will not be accessible.

The users have been relocated but the building remains in operation. Signage will be installed to advise users of new access points.

Classrooms in this area will remain operational.

April 15, 2022 to July 24, 2022 Phase B (Raymond Building - complete closure) General construction Moderate to high levels of noise in the construction zone. Multiple shutdowns, areas will not be accessible.

The users have been relocated but the building remains in operation. Signage will be installed to advise users of new access points.

April 15, 2022 to November 30, 2022 Phase 2 (Barton link exterior) Roof and mechanical system installation Loud noise and vibrations and access restrictions. Noisy work will be done during the summer. Access restrictions and new access points will be communicated through signage.
September 1, 2022 to mid-July 2023 Phase C (Raymond West Wing) General construction Moderate to high levels of noise in the construction zone. Multiple shutdowns, areas will not be accessible. The users have been relocated but the building remains in operation. Signage will be installed to advise users of new access points.
January 2, 2023 to July 24, 2023 Phase 3 (Raymond exterior)

Roof, French drains and entrance

Low to moderate levels of noise (general construction activity) and access restrictions.

Access restrictions and new access points will be communicated through signage.
April 1, 2023 to July 24, 2023 Phase 4 (Raymond exterior) Landscaping Low levels of noise, access restrictions. Access restrictions and new access points will be communicated through signage.

 