Otto Maass, Pulp and Paper renovation update

Published: 10 March 2011

Otto Maass

  • Third floor west block laboratories are finished and are now in use by researchers.
  • Third floor corner block laboratories are partially finished and researchers are moving back in.
  • Asbestos removal in the north block is complete. Construction will begin in the penthouse and 4th floor, north block, on March 14.

Pulp and paper

  • Construction has begun in the basement, now that asbestos abatement has been completed.
  • Asbestos removal is finished on the second floor. Construction has begun on the south side of the second floor.

 