Nouvelles

Construction Start: Wong Building - Space simulator

Publié: 4 December 2023

McGill University has mandated Corenov Constructeurs Inc to carry out the following project: Wong Building / 20-094 - Space simulator.

Project manager: Mona Modarressi - mona.modarressi [at] mcgill.ca

Assistant project managers: Mark Grzywacz - mark.grzywacz [at] mcgill.ca; Thomas Perreault - thomas.perreault [at] mcgill.ca

Construction start: December 2023

Planned construction end date: March 2024

Work schedule: Mondays to Fridays, 6 a.m. to 3 p.m. Any additional hours will be coordinated.

Scope of work: 

The project consists of the renovation of two laboratories (rooms 3062 and 3064) to accommodate the installation of a space simulator. The planned work includes a reorganization of the compressed air system, the installation of electrical outlets, electrical conduits and data wiring conduits, as well as modifications to the HVAC systems.

Impact:

Service shutdowns will be required. Users will be informed in advance.