News
Construction Start: Burnside Hall - Modernization of the elevators
Please be advised that McGill University has mandated Adams Elevators Inc. to carry out the following project: 17-004 Burnside - Modernization of the elevators.
Construction start date (UPDATED): June 2024
Planned construction end date: March 2025
Work schedule: Monday to Friday 6 a.m. to 3 p.m.
Project Manager: Simon Lacoste - simon.lacoste [at] mcgill.ca
Assistant Project Manager: Jose Uria - jose.uria [at] mcgill.ca
Contact for building users: Jose Correa (Building Director) - jose.a.correa [at] mcgill.ca
Scope of work: Modernization of the three elevators (cabin, controls, doors and mechanicals components).
Impact & mitigation: One elevator will be out of operation at a time as work is performed on it.